A project costs 200k€ and pays 110k€ at the end of each of years 1 and 2. At r=10%r = 10\%, set the slider to its NPV in k€.

Estimate on a scale from -50k€ (-50) to +50k€ (50).

Hints
  1. 110/1.1=100110/1.1 = 100; 110/1.2190.9110/1.21 \approx 90.9.
  2. Sum the PVs and subtract 200.
Show the answer

-9.1 (answers within ±3 count)

Why

NPV=200+100+90.9=9.1NPV = -200 + 100 + 90.9 = -9.1k€. The undiscounted total (+20k€) looked fine, discounting exposes the loss. That gap is the whole reason NPV exists.