Practice question · Estimate
A project costs 200k€ and pays 110k€ at the end of each of years 1 and 2. At , set the slider to its NPV in k€.
Estimate on a scale from -50k€ (-50) to +50k€ (50).
Hints
- ; .
- Sum the PVs and subtract 200.
Show the answer
-9.1 (answers within ±3 count)
Why
k€. The undiscounted total (+20k€) looked fine, discounting exposes the loss. That gap is the whole reason NPV exists.
Practise NPV and IRR
The app has 7 more questions on this lesson, and keeps your place in the course. Business I is free to start.
More questions on NPV and IRR
- A project’s IRR is 18% and the firm’s cost of capital is 11%. By the IRR rule, what should the firm do?
- Order the steps of a discounted-cash-flow appraisal.
- Two projects both have an IRR of 20%. One is a 5,000€ kiosk, the other a 5 million€ factory. Why does the…
- Match each appraisal concept to its meaning.