Painting I / Oil, Fat Media and the Rule of Fat Over Lean
Practice question · Estimate

An ordinary oil painting should not be varnished until the film is dry through. How many months is the usual minimum given for that?

Estimate on a scale from 0 months (0) to 24 months (24).

Hints
  1. It is far longer than touch-dry.
  2. The conventional figure is half a year.
Show the answer

6 (answers within ±2 count)

Why

Conventionally about six months, and longer for a thick film. The figure is a rule of thumb rather than a measurement: what actually matters is the thickness, the pigments and the room it dried in, so a heavily impasted picture can still be moving after a year while a thin one is stable in three months.

Read the lesson: Oil, Fat Media and the Rule of Fat Over Lean →

Practise Oil, Fat Media and the Rule of Fat Over Lean

The app has 7 more questions on this lesson, and keeps your place in the course. Painting I is free to start.